NapaSan Construction Zones

NapaSan conducts a regular sewer system maintenance program. You may see us on the streets, repairing, replacing, or cleaning sewer lines or recycled water pipes. We apologize for any inconvenience and appreciate your patience while we work to keep our system operating effectively! 

Refer to the information below to find out where our current construction projects are happening. If you have any questions or concerns, please call NapaSan at (707) 258-6000. 

Browns Valley Trunk Sewer Project

Project Manager: Andrew Damron, adamron@napasan.com

Project Background: The Browns Valley Trunk Project is designed to intercept wastewater from Browns Valley and Southwest Napa and divert the flow away from sewer lines that are over capacity via a new 3-mile pipeline that will deliver the wastewater to NapaSan for treatment.  For additional background information, visit our Browns Valley Trunk Project page.   

Current Construction Location:   During the week of July 19, pipeline installation will occur on Freeway Drive at the Laurel/Kilburn intersection.  Sewer laterals will be connected along Freeway Drive from Old Sonoma to Elm Street.  Concrete restoration work will occur at various locations throughout the project area. 

During the week of July 26, pipeline and manhole installation will take place on Freeway Drive at the Old Sonoma Road intersection.  Pipeline and manhole installation will also take place on Freeway Drive at the Pine Street intersection and along Browns Valley Road from the area of Robinson Lane to Thompson Avenue.  Sewer pipe abandonment work will take place at various manholes along Freeway Drive.  Concrete restoration work will occur at various locations throughout the project area. 

7.19.21 Browns Valley Trunk Sewer Project Construction Location Map


2021 Collection System Rehabilitation Project

Project Manager: Karl Ono, kono@napasan.com

Project Background: The 2021 Collection System Rehabilitation Project is essential to reduce the amount of maintenance calls, decrease the potential for sewer overflows in the project area,  and improve the operation of our sewer system. 

KJ Woods Construction, Inc. is expected to begin construction in March 2021, and work is planned to continue through October 2021. All work will be done in accordance with County and State public health guidelines related to the COVID-19 pandemic.

The project area was selected due to the deteriorated condition of aging sewer pipes. NapaSan will be repairing or replacing these aging sewer pipelines that allow stormwater and groundwater to infiltrate into the sewer system. Reducing this infiltration helps to decrease the possibility of sewer overflows and spills. Approximately 430 sewer laterals will be repaired or replaced as part of this project. Through this project, 4.2 miles of pipeline (approximately 1.6% of the total sewer system) will be rehabilitated or replaced. 

As always, NapaSan will work to minimize negative impacts to businesses and residents whenever possible throughout this project. Wherever possible, pipelines will be rehabilitated using trenchless methods, which minimize costs, construction time, and neighborhood disruptions compared to traditional open-cut trenching. 

Subscribe here to receive weekly email or text updates regarding the 2021 Collection System Rehabilitation Project.

Current Construction Location:  

During the week of July 5, No work will occur on July 5 in observance of Independence Day. Beginning on July 6, pipeline rehabilitation work will continue on Lincoln Avenue between Jefferson Street and Adrian Street.  Pipeline rehabilitation work will also take place on Yajome Street between Pueblo Avenue and Lincoln Avenue.

During the week of July 12, pipeline rehabilitation work will continue on Lincoln Avenue between Jefferson Street and Adrian Street and on Yajome Street between Pueblo Avenue and Lincoln Avenue.

Map of 2021 Collection System Rehabilitation Project Area